Saturday, June 27, 2009
Tuesday, June 23, 2009
Monday, June 22, 2009
6-22-09 (Monday)
Saturday God's spirit filled the air and hearts of many people, who helped clean-up and final grade Grandma Bet's lot in preparation for sod being installed this week. The morning was capped off with hamburgers and hot dogs prepared by Mrs. Pudding and Lisa. Thanks goes out to all who helped God on Saturday bring Grandma Bet's blessing closer and closer to completion.
We passed our final inspection today and hope tomorrow to obtain our Certificate of Occupancy. This project stands as proof...THERE IS NO LIMIT TO WHAT GOD CAN DO!!!
Wednesday, June 10, 2009
6-10-09 (Wednesday)
Progress continues this week with:
Mike Corby (pictured) finishing the master bathroom shower tile.
C & C Plumbing finishing the plumbing top-out.
Bo Seignious installing the interior door hardware.
Tom Wrenn finishing the fascia installation.
Bevis Concrete pouring the driveway and sidewalk.
As you can see, we are moving closer and closer to final inspection.
Thursday, June 4, 2009
6-4-09 (Thursday)
Progress continues today with:
Bevis Construction crews forming the driveway and sidewalk.
Central Contractors crews installing the microwave and driveway sleeves for irrigation and electrical.
West Coast Insulation crews installing the shelving and bathroom mirrors.
Mike Corby continuing the master bathroom shower tile installation.