Monday, April 18, 2011

CONSTRUCTION UPDATE

The water meter has been set by the Town of Lake Placid along with a temporary water supply connection by C & C Plumbing. Sorry to say...that we have hit a little road block with the site and concrete slab scope of work. There is a substantial elevation drop from one side of the property to the other, which is effecting our original (approved) concrete slab design. Last week I had a meeting with Bo Seignious, Grif Broach, and Steve Blount to discuss this issue, and concluded that we need to revise the foundation drawings showing a stem wall type foundation, submit to the engineer for approval, and resubmit these drawings to the Building Department for final approval. While this process is taking place, Steve Blount is going to go ahead and start moving dirt around so that we can establish a finished floor elevation.